Change Orders: Price Them Before the Work, Log Them the Same Day

Short answer: A change order is any change to the agreed scope after signing — an added outlet, a moved wall, a upgraded window. Each one changes the price. The discipline that saves budgets: no change gets built before its price is agreed in writing, and every agreed change lands in the budget the same day.

Worked example: small changes, real money

The sample build carries $2,050 of change orders so far ($1,200 foundation, $850 plumbing) inside its $458,500 projected total. Individually trivial — but change orders compound: ten "small" $850 changes are $8,500, and late-stage changes (after drywall) routinely cost 2–3× the same change made at framing. The Home Build Tracker keeps a change-order column per line so the running total is never a surprise.

A change-order habit that works

FAQ

Are change orders marked up?

Often — many contracts apply the builder's fee or a stated markup to changes. Know your contract's rule; the tracker logs the agreed all-in price either way.

What about changes the builder suggests?

Some are genuine improvements, some are scope the original price should have covered. If it's in the plans, it's not a change — check the drawings before signing the order.

Can a change order reduce the price?

Yes — de-scoping creates a credit change order (negative). Log it the same way; credits forgotten are credits lost.

Keep the running total visible: every change lands in the projected cost immediately.

Open Home BuildSee Pro — $5/mo

Run your own numbers: try the free Home Build Budget Tracker with your price, shipping and costs.

Open the Home Build Budget TrackerSee Pro — $5/mo

One Pro for all 6 tools — $5/mo or $50/yr

Saved work and no ads across the fee calculator, Flip Profit, DIY Cost, Craft Fair, Camp Splitter and Home Build Tracker.

See Pro — $5/mo